Name of Project

Isle of Skye Open Space Wall Repairs

Client

Friends of Isle of Skye

Role of Groundwork

  • Carried out condition survey of dry stone walls
  • Set brief and advised on selection of structural engineer
  • Advised on selection of Dry Stone walling contractors
  • Lead Consultant for Community Spaces funding

Description of Project

The Friends of the Isle of Skye are  keen to preserve and improve the area and approached Groundwork for support and advice. Key issues were the preservation of the Dry Stone walls and making them safe to the public. Repair work started on the walls in 2011.

Value of Work

£40,000

Funders

Community Spaces

Key Target Dates

Preparation by Groundwork since March 2009

Dry Stone walling commenced work on site March 2011